Problems with the Army’s troubled Ajax light tank programme are so deep-rooted they may never be resolved, the Whitehall spending watchdog has warned.
In a scathing report, the National Audit Office (NAO) said the £5.5 billion project was “flawed from the start”, with the Ministry of Defence (MoD) failing to understand the scale and complexity of the work it was undertaking.
It said delays to programme – which is already more than four years behind schedule – could now jeopardise plans to restructure the Army around a new generation of digitally-enabled armoured fighting vehicles.
Ministers publicly acknowledged last year that the programme was in trouble and have been making regular updates to Parliament on the situation.
They included problems with excessive noise and vibration which have left dozens of troops needing urgent hearing assessments after taking part in trials on the vehicles.
General Dynamics UK (GD) was contracted to supply 589 Ajax armoured vehicles, which were originally supposed to enter service in 2017, but despite receiving more than £3 billion just 26 have so far been delivered.
The NAO said the concerns around noise and vibration have still to be resolved, and continued to represent a “significant risk” to the programme.
The MoD and GD continued to disagree on the safety of the vehicles and whether contractual requirements had been breached – a dispute that was likely to take until late this year before it can be resolved.
While trials with Army crews have been halted, the NAO said GD has continued production without receiving any payment in 2021.
However, the MoD has yet to set a revised initial operating capability date and has no confidence that an April 2025 target date for full operating capability can be met, leaving the Army to rely on its ageing Warrior armoured fighting vehicles.
“It is not yet clear whether the programme’s issues are resolvable,” the NAO said.
“The department will need to consider carefully whether the programme can deliver the intended capabilities but does not expect to be in a position to do so until late 2022.”
Delays
The NAO blamed the complexity of the programme – with around 1,200 capability requirements – for the problems, which had resulted in a series of disputes and delays.
The head of the NAO Gareth Davies said: “The Ministry of Defence and GD’s approach was flawed from the start.
“They did not fully understand the scale or complexity of the Ajax programme and a series of failures have led to delays and unresolved safety issues that will have a significant impact on the Army’s ability to use the vehicles.”
The Commons Public Accounts Committee chair Dame Meg Hillier called on the two sides to resolve their differences as quickly as possible
“The NAO report reads like a checklist for major project failure where almost everything that can go wrong, did go wrong,” she said
“The Army is forced to continue using increasingly old and obsolete equipment which, aside from adding cost, reduces our capability at a time when dangers are only increasing.
“Both parties must find a way out of the deadlock, work together to rescue the programme, and ensure the Army gets the equipment it needs.”
A MoD spokesman said: “As we have made clear, Ajax is a troubled programme, and we will not accept a vehicle that is not fit for purpose.
“As the NAO recognises, we are working with General Dynamics to resolve the noise and vibration issues with a view to Ajax being successfully delivered to the Army.
“We continue to meet our obligations to Nato and will mitigate any capability gap through a range of alternative reconnaissance capabilities.”
Related: £5.5bn Ajax tanks: ‘Biggest defence procurement failure of past decade’